Contact
18-04809 Single Family Residence - Addition
Address:
3545 MATHEWS DR NW
BREMERTON,  WA  98312
Parcel #: 4635-000-017-0006
Status: Reviewing revisions submitted by applicant after permit issuance.
Submitted: 10/1/2018
Approved: 6/26/2019
Issued: 6/26/2019
Closed:
Expires: 7/3/2021
Inspections:
Required: 22
Complete: 6
Total Fees:
$1,60212
Additional fees may be required
Project: MORTVEDT (Cottage 1) - Addition to second floor, remodel existing home and decks

Public Notice
Description Begin Date End Date

Contacts
:
MORTVEDT DEREK
:
MORTVEDT DEREK
:
King, Matt
:
Burt Engineering PLLC
:
HOWELL, COLLIN M
:
BLUE ARCHITECTURE & INTERIORS

Contractors

Details

Parcels
Parcel(s) associated with your permit.
Parcel Owner Address
4635-000-017-0006 MORTVEDT DEREK 3549 MATHEWS DR NW
BREMERTON,  WA 98312

Submittals

Upload documents in PDF format on the following screen. The name of each file should simply identify what each submittal document is. Examples: “Floor Plans”, “Engineered Structural Plans”, "Engineered Civil Plans", “Site Plan”

Click the files link on the far right of the submittal item to upload. The files link will indicate how many documents have been uploaded.

Not uploading all required submittal documents will delay the processing of your permit.

Submittal Required Received Accepted
Miscellaneous inspection documents No n/a
Approved Permit Documents and Plans: Print all files and keep onsite for inspections Yes 6/26/2019 6/26/2019
Please Download and Review All Documents: This line contains your detailed information request and when applicable, permit documents with reviewer comments No n/a
Information Request: Upload a letter response AND any revised, corrected, or additional documentation. No 3/13/2019 3/13/2019
Completed Online Permit Form No 10/1/2018 10/9/2018
Site Plans No n/a
Construction Plans No n/a
Engineered construction plans No n/a
Kitsap Public Health District Documentation (Septic Only) No 10/9/2018 10/9/2018
Engineer's supporting calculations No n/a
Energy Code Worksheet No n/a
Letter of Authorization No 10/1/2018 10/9/2018

Approval Steps
Follow your application through the approval process.
Step Status Date
Building Height Review Approval Step Not Required (Deleted) 10/9/2018
Health District Approval Processing for Building Permits Approved 10/9/2018
Environmental Review Approved 3/18/2019
Residential Zoning Review Approved 6/26/2019
Stormwater Review Approval Step Not Required (Deleted) 10/9/2018
Building Code Plan Review Approved 3/19/2019
Fire Marshal Review Approval Step Not Required (Deleted) 10/31/2018

Reviews
Start Complete Applicant Response
10/29/2018 11/28/2018 3/11/2019
3/11/2019 4/2/2019 6/26/2019
6/26/2019 6/26/2019

Fixtures
Fixture Quantity Per Unit Value
R-Clothes Dryer with Exhaust, Electric 1 $0.00 $0.00
R-Cook Stove with Exhaust, Electric 1 $0.00 $0.00
R-Sink (Lavatory, Kitchen, Mop or Bar Sink) 3 $0.00 $0.00
R-Water Heater 1 $0.00 $0.00
R-Tub and/or Shower Unit 1 $0.00 $0.00
R-Bath Fan and/or Exhaust Fan 2 $0.00 $0.00
R-Clothes Washing Machine 1 $0.00 $0.00
R-Water Closet and/or Urinal 2 $0.00 $0.00
R-Dish Washer 1 $0.00 $0.00
Ductless Split System 1 $0.00 $0.00
Total: $0.00

Valuations

Valuations and fees will be validated during the review process.

Valuation Quantity Rate Value
New Residential Floor Space, Second Floor - Enter Square Footage 443.00 $116.15  / SQFT $51,454.45
Major remodel to residential space - Enter Square Footage 449.00 $69.69  / SQFT $31,290.81
New covered porch, carport, covered deck - Enter Square Footage 126.00 $23.23  / SQFT $2,926.98
Total: $85,672.24

Fees

Fee totals below may not reflect all fees, including fees calculated by hourly rates.

Fee Amount
Building Permit Fee, Residential $1,490.71
Technology Fee $14.91
State Surcharge DCD $6.50
Permit Center Base Fee $90.00
Total : $1,602.12

Bonds
Type Number Amount Issued Expires Completed

Inspections

The inspections listed below are standard for all permits of this type and may not apply to your specific permit. Once your permit has been issued, all inspections listed are applicable to your permit. Note: Community Development Building Final Inspections (B-Final), Commercial CO Inspection Fire Marshal (FM-CO-Final) and the Final Field Inspections (DE-FFI) are not eligible for next day inspection requests. Please allow two business days when requesting a Final inspection.

Completed On
Pre-issuance inspection for Road Approach.
Residential Temporary Silt & Erosion Control Inspection.*Note: This is not a standalone inspection, it will be done with all building inspections and will not be approved until final inspection. You will not need to request this inspection unless you're instructed to by your Inspector.
Flood Plain
Residential Foundation, Footing Inspection 3/25/2020
Residential Footing, Deck or Porch inspection
Residential Foundation, Stem Wall Inspection
Residential Underfloor framing (prior to sub-floor) 6/23/2020
Residential Exterior Shear Wall Nailing Inspection 9/29/2020
Residential Interior Shear Wall Nailing Inspection
Residential Plumbing, Rough-In Inspection 10/9/2020
Residential Mechanical, Ventilation Rough-In Inspection
Residential Ductless Split System Rough-In Inspection 1/4/2021
Residential Framing Inspection
Residential Insulation Inspection
Residential Gypsum Wallboard Inspection
Road approach form inspection prior to pour
Road Approach - Final
Driveway Full Dispersion
Flood Plain
Health District Final (Final Must Be Approved Prior To Scheduling Final Building Inspection)
Residential Final Building Inspection
Requested permit extension 6/25/2020

Structures
Structure Use Occupancy Type Square Footage
MORTVEDT (Cottage 1) - Addition to second floor, remodel existing home and decks Residential, one or two family dwelling 1018

Conditions

The conditions listed below are standard for all permits of this type and may not apply to your specific permit. Once your permit is issued, all conditions listed are applicable to your permit.

Permit Expiration: Building permits expire 365 days after permit issuance, or 180 days after the last approved inspection activity is performed. The Building Official may extend the time for action for a period not exceeding 180 days, upon the receipt of a written extension request indicating that circumstances beyond the control of the permit holder have prevented action from being taken. Additional fees may be due to reactivate the permit.
ELECTRICAL WORK. If electrical work is proposed, a separate electrical permit is required. You can contact Labor and Industries (L&I) at www.lni.wa.gov to obtain an electrical permit. Electrical systems must be inspected by L&I prior to requesting a framing inspection and final approval granted prior to requesting a final building inspection from the Department of Community Development.
Reinspection Fee: All approved plans for this permit and the printed building permit with conditions are required to be on-site for inspection purposes, and work to be inspected shall be complete and ready for inspection. If an inspection is called for and plans are not available on site, or the work is not ready for inspection, or if previously identified corrections have not been made, approval will not be granted. In addition, a re-inspection fee will be charged and must be collected by the Department of Community Development prior to any further inspections being performed or approvals granted.
Final Inspection Required: All building permits shall have a final inspection performed and approved by the Kitsap County Department of Community Development prior to permit expiration. The failure to request a final inspection or failure to obtain final approval prior to expiration will be documented in the legal property records on file with Kitsap County as being non-compliant with Kitsap County ordinances and building regulations and will be referred to Kitsap County Code Compliance for action.
Erosion and sedimentation control devices shall be installed in accordance with best management practices. Provide silt fence(s) along contours. Provide appropriate gravel construction entrance mat. Protect all exposed soils.
All structures shall have roof gutters. All gutters, downspouts, and yard drains must be directed at a minimum to splash blocks, (or an infiltration system, if required). Drains shall have a minimum 2% grade away from the foundation. All drainage discharges shall be located so that there is no adverse impact to downstream or adjacent properties.
This permit shall comply with all Kitsap Public Health District regulations and conditions of approval.
Drainage BMP: Infiltration Pit Connect all roof drains to the infiltration trench system as shown on the approved plans. Pit Size: Depth of Pit: 2 feet; Depth of Rock: 1.5 feet Minimum Cover: 6 inches Upslope: Setback 30 feet from drainfield, 10 feet from curtain drain Downslope: Setback 10 feet from drainfield Setback: 10 feet from property line Setback: 10 feet from structures The infiltration pit shall be inspected prior to covering; and shall be completed prior to requesting a final building inspection.
Drainage BMP: Dispersion Trench Connect all roof drains to the dispersion trench system as shown on the approved plans. Trench length: Trench width: 2 feet Trench depth: 18 inches Downslope: Setback 10 feet from drainfield Setback: 10 feet from property line Setback: 10 feet from structures Applicant shall complete the provided Operation & Maintenance Manual for privately maintained dispersion trench facilities. The completed Operation & Maintenance Manual shall be submitted to Kitsap County and the dispersion trench shall be inspected prior to requesting a final building inspection.
Drainage BMP: Gravelless Chamber Connect all roof drains to the gravelless chambers as shown on the approved plans. Number of chambers: Length of chambers: Where more than 1 chamber, set at a minimum of 6 foot on center 3 inches of gravel is required below the chambers. Trenches must be gravel-filled outside of the chambers to the top of the chamber louvers. The infiltration chambers shall be inspected prior to covering.
Drainage BMP: Bioretention Connect all roof drains to the bioretention cell as shown on the approved plans. Bottom Square Footage of Cell: Ponding Depth, 12” maximum: Engineered Soil Depth: 18 inches Side slopes: 3H:1V Setback, upslope from drainfield: 30 feet Setback, downslope from drainfield: 30 feet Setback from property line: 10 feet Setback from structures: 10 feet Bioretention area shall be protected to minimize compaction of underlying soils during construction. Bioretention system shall be inspected prior to requesting a final building inspection.
Drainage BMP: Rain Garden Direct runoff to rain garden, via a swale, pipe, or across landscaped area Bottom Square Footage of raingarden: Ponding depth, 12” maximum: Engineered Soil depth: 18 inches Side slopes: 2H:1V Setback, upslope from drainfield: 50 feet (raingarden handbook) Setback, downslope from drainfield: 10 feet (raingarden handbook) Setback from property line: 10 feet Setback from structures: 10 feet The rain garden shall be inspected prior to requesting a final building inspection.
Drainage mitigation method: Site Development Activity Permit (SDAP) All site plan construction and stormwater systems shall be installed as designed per SDAP #: Stormwater mitigation that does not match the approved SDAP will not be allowed without further SDAP review by Kitsap County Department of Community Development
This permit shall comply with all of the conditions of approval of the land segregation for SAULSBERRY VILLA TRACTS, AS PER PLAT RECORDED IN VOLUME 4 OF PLATS, PAGE 117, RECORDS OF KITSAP COUNTY; >>TOGETHER WITH THE SOUTHWESTERLY 7.22 FEET OF TRACT 18 PER BOUNDARY LINE ADJUSTMENT RECORDED UNDER AUDITOR'S FILE NO. 9510030180
Project must comply with Title 15 Flood Hazard Areas. Inspector to verify the information on the submitted Elevation Certificate. Stairs and decks shall be constructed with flood proof construction. Utilities shall be elevated 1' above the Base Flood Elevation (13').

Required Permits
Type Requirement For Number Status

Notes

Associations