19-03657 Single Family Residence - New
Address:
19832 NW STAVIS BAY RD
SEABECK,  WA  98380
Parcel #: 4446-000-014-0008
Status: Permit has been re-issued (after expiration or after being revised).
Submitted: 8/11/2019
Approved: 10/18/2019
Issued: 10/21/2019
Closed:
Expires: 8/22/2021
Inspections:
Required: 38
Complete: 18
Total Fees:
$7,04553
Additional fees may be required
Project: GABLE - New cabin

Public Notice
Description Begin Date End Date

Contacts
:
Wandling, Paul
:
GABLE G BRIAN & JILL M
:
Brian Gable
:
Jerry Kierig
:
Keith Kayser
:
Moran, Jerry

Contractors

Details
Impact Fee Land Category: 210
Impact Fee Units: 1

Parcels
Parcel(s) associated with your permit.
Parcel Owner Address
4446-000-014-0008 GABLE G BRIAN & JILL M 19832 NW STAVIS BAY RD
SEABECK,  WA 98380

Submittals

Upload documents in PDF format on the following screen. The name of each file should simply identify what each submittal document is. Examples: “Floor Plans”, “Engineered Structural Plans”, "Engineered Civil Plans", “Site Plan”

Click the files link on the far right of the submittal item to upload. The files link will indicate how many documents have been uploaded.

Not uploading all required submittal documents will delay the processing of your permit.

Submittal Required Received Accepted
Miscellaneous inspection documents Yes 6/12/2020
Approved Permit Documents and Plans: Print all files and keep onsite for inspections No 10/21/2019 10/21/2019
Information Request: Upload a letter response AND any revised, corrected, or additional documentation. Yes 10/5/2019 10/10/2019
Please Download and Review All Documents: This line contains your detailed information request and when applicable, permit documents with reviewer comments No 10/1/2019 10/1/2019
Upload Required Permit Documents as listed on your Required Permit Questionnaire at http://kcowa.us/permitapp Yes 8/27/2019 9/3/2019

Approval Steps
Follow your application through the approval process.
Step Status Date
PW - Concurrency Test Review Approved 9/6/2019
Permit Center Processing - Building Approved 9/3/2019
Building Height Review Approval Step Not Required (Deleted) 8/23/2019
Health District Approval Processing for Building Permits Approved 8/23/2019
Environmental Review Approved 9/27/2019
Residential Zoning Review Approved 9/23/2019
Stormwater Review Approved 10/18/2019
Building Code Plan Review Approved 9/30/2019
Road Approach Research Approved 9/3/2019
Road Approach Approval Approved 9/13/2019
Addressing, Verification/Assignment Approved 9/23/2019
PW - ROW Review Approved 9/27/2019
Fire Marshal Review Approval Step Not Required (Deleted) 9/3/2019

Reviews
Start Complete Applicant Response
9/3/2019 9/30/2019 10/5/2019
10/5/2019 10/18/2019

Fixtures
Fixture Quantity Per Unit Value
R-Clothes Dryer with Exhaust, Electric 1 $0.00 $0.00
R-Gaspipe System LPG/NATL/OIL 1 $0.00 $0.00
R-Fireplace-Wood, or Wood Stove 1 $0.00 $0.00
R-LP or Natural Gas Water Heater Vent & Combustion Air 1 $0.00 $0.00
R-Miscellaneous Mechanical Equipment 1 $0.00 $0.00
R-Propane fuel tank 500 gallons and under 1 $0.00 $0.00
R-Sink (Lavatory, Kitchen, Mop or Bar Sink) 3 $0.00 $0.00
R-Water Heater 1 $0.00 $0.00
R-Tub and/or Shower Unit 2 $0.00 $0.00
R-Bath Fan and/or Exhaust Fan 2 $0.00 $0.00
R-Hose Bibs 2 $0.00 $0.00
R-Clothes Washing Machine 2 $0.00 $0.00
R-Dish Washer 1 $0.00 $0.00
R-Cook Stove with Exhaust, LP or Natural Gas 1 $0.00 $0.00
Total: $0.00

Valuations

Valuations and fees will be validated during the review process.

Valuation Quantity Rate Value
Finished Residential Floor Space within a daylight basement - Enter Square Footage 751.00 $120.75  / SQFT $90,683.25
New Deck, Uncovered - Enter Square Footage 363.00 $15.70  / SQFT $5,699.10
New Residential Floor Space, Main (1st) Floor - Enter Square Footage 751.00 $120.75  / SQFT $90,683.25
New covered porch, carport, covered deck - Enter Square Footage 30.00 $24.15  / SQFT $724.50
Total: $187,790.10

Fees

Fee totals below may not reflect all fees, including fees calculated by hourly rates.

Fee Amount
Road Impact Fee With CPI Modifier $699.46
Park Impact Fee With CPI Modifier $703.72
State Surcharge DCD $6.50
First Half of Permit Residential Fee $1,539.89
Technology Fee $30.80
Permit Center Base Fee $90.00
School Impact Fee With CPI Modifier $1,378.52
Simplified Drainage Review (Engineered) $1,040.00
Blue Address sign Including Shipping $16.75
Second Half of Permit Residential Fee $1,539.89
Total : $7,045.53

Bonds
Type Number Amount Issued Expires Completed

Inspections

The inspections listed below are standard for all permits of this type and may not apply to your specific permit. Once your permit has been issued, all inspections listed are applicable to your permit. Note: Community Development Building Final Inspections (B-Final), Commercial CO Inspection Fire Marshal (FM-CO-Final) and the Final Field Inspections (DE-FFI) are not eligible for next day inspection requests. Please allow two business days when requesting a Final inspection.

Completed On
Residential Foundation, Monolithic Slab Inspection 7/30/2020
Residential Drainage Inspection - Downspout system (prior to backfill) 6/29/2020
Residential Dampproofing to enclose habitable space below grade inspection. 6/29/2020
Pre-issuance inspection for Road Approach. 9/6/2019
Residential Temporary Silt & Erosion Control Inspection.*Note: This is not a standalone inspection, it will be done with all building inspections and will not be approved until final inspection. You will not need to request this inspection unless you're instructed to by your Inspector. 6/29/2020
Residential Foundation, Footing Inspection 3/11/2020
Residential Foundation, Stem Wall Inspection 2/12/2021
Plumbing, Underground Piping Inspection 7/27/2020
Mechanical, Radiant Floor Tubing Inspection 7/30/2020
Below Grade Slab Insulation Inspection 7/30/2020
Residential Footing, Deck or Porch inspection 2/23/2021
Residential Underfloor framing (prior to sub-floor) 2/12/2021
Residential Exterior Shear Wall Nailing Inspection 9/1/2020
Residential Interior Shear Wall Nailing Inspection
Residential Plumbing, Rough-In Inspection 2/11/2021
Residential Mechanical, Ventilation Rough-In Inspection 2/11/2021
Residential Mechanical, Interior Gas Piping Inspection 1/21/2021
Residential Mechanical Fireplace Rough-In Inspection
Residential Framing, Deck or Porch inspection
Residential Framing Inspection 2/23/2021
Residential Mechanical, Household Appliance
Residential Insulation Inspection
Residential Gypsum Wallboard Inspection
Residential Mechanical, Propane or Liquid Fuel Tank & Piping Inspection 1/21/2021
Residential Gas Stove Installation Inspection
Pre-bioretention soil placement
Bioretention soil placement and pre-mulch/planting
Post mulch/planting and construction site inspection
Infiltration Pit - Stormwater System Inspection
Dispersion Trench
Rain Garden Inspection
Driveway Full Dispersion
Road approach form inspection prior to pour
Road Approach - Final
Health District Final (Final Must Be Approved Prior To Scheduling Final Building Inspection)
Deferred Impact Fees Must be paid in full before requesting final inspection. Please call 360-337-5777.
Residential Final Building Inspection
Residential Certificate of Occupancy Approval Inspection

Structures
Structure Use Occupancy Type Square Footage
GABLE - New cabin Residential, one or two family dwelling 1895

Conditions

The conditions listed below are standard for all permits of this type and may not apply to your specific permit. Once your permit is issued, all conditions listed are applicable to your permit.

Permit Expiration: Building permits expire 365 days after permit issuance, or 180 days after the last approved inspection activity is performed. The Building Official may extend the time for action for a period not exceeding 180 days, upon the receipt of a written extension request indicating that circumstances beyond the control of the permit holder have prevented action from being taken. Additional fees may be due to reactivate the permit.
ELECTRICAL WORK. If electrical work is proposed, a separate electrical permit is required. You can contact Labor and Industries (L&I) at www.lni.wa.gov to obtain an electrical permit. Electrical systems must be inspected by L&I prior to requesting a framing inspection and final approval granted prior to requesting a final building inspection from the Department of Community Development.
Reinspection Fee: All approved plans for this permit and the printed building permit with conditions are required to be on-site for inspection purposes, and work to be inspected shall be complete and ready for inspection. If an inspection is called for and plans are not available on site, or the work is not ready for inspection, or if previously identified corrections have not been made, approval will not be granted. In addition, a re-inspection fee will be charged and must be collected by the Department of Community Development prior to any further inspections being performed or approvals granted.
Final Inspection Required: All building permits shall have a final inspection performed and approved by the Kitsap County Department of Community Development prior to permit expiration. The failure to request a final inspection or failure to obtain final approval prior to expiration will be documented in the legal property records on file with Kitsap County as being non-compliant with Kitsap County ordinances and building regulations and will be referred to Kitsap County Code Compliance for action.
Certificate of Occupancy Approval Inspection. No building or structure shall be used or occupied, until the final inspection and the occupancy approval inspection have been approved. Approval of the certificate of occupancy inspection shall not be construed as an approval of any violation of the provisions of this code or of other ordinances of the jurisdiction. Certificates presuming to give authority to violate or cancel the provisions of this code or other ordinances of the jurisdiction shall not be valid.
Residential Address: Numerals for residential building addresses shall be conspicuously displayed on a contrasting background and shall be a minimum of 4 inches in height with a minimum stroke of 1/2 inch. If the building is not clearly visible from a named way of travel, the numerical designation (address) shall also be displayed near the main entrance to the property as well as at the driveway entrance that leads to the building. Property addresses shall be posted prior to requesting any inspections. If property addresses are not posted upon inspection, inspection will not be approved and a re-inspection fee will be charged and must be collected by the Department of Community Development prior to any further inspections being performed or approvals granted.
Erosion and sedimentation control devices shall be installed in accordance with best management practices. Provide silt fence(s) along contours. Provide appropriate gravel construction entrance mat. Protect all exposed soils.
All structures shall have roof gutters. All gutters, downspouts, and yard drains must be directed at a minimum to splash blocks, (or an infiltration system, if required). Drains shall have a minimum 2% grade away from the foundation. All drainage discharges shall be located so that there is no adverse impact to downstream or adjacent properties.
This permit shall comply with all Kitsap Public Health District regulations and conditions of approval.
No final inspection or occupancy approval will be granted until all impact fees are paid. This permit is subject to the payment of impact fees. Impact fees must be paid at time of permit issuance, or if deferred, must be paid prior to final inspection.
Construct per Section (AA) of the Exhibit. Grade approach to drain away from County Roadway. Pave approach from existing road to edge of Right of Way/Property line or 13 feet, whichever is greater. No culvert pipe required.
Drainage BMP: Infiltration Pit Connect all roof drains to the infiltration trench system as shown on the approved plans. Pit Size: Depth of Pit: 2 feet; Depth of Rock: 1.5 feet Minimum Cover: 6 inches Upslope: Setback 30 feet from drainfield, 10 feet from curtain drain Downslope: Setback 10 feet from drainfield Setback: 10 feet from property line Setback: 10 feet from structures The infiltration pit shall be inspected prior to covering; and shall be completed prior to requesting a final building inspection.
Drainage BMP: Dispersion Trench Connect all roof drains to the dispersion trench system as shown on the approved plans. Trench length: Trench width: 2 feet Trench depth: 18 inches Downslope: Setback 10 feet from drainfield Setback: 10 feet from property line Setback: 10 feet from structures Applicant shall complete the provided Operation & Maintenance Manual for privately maintained dispersion trench facilities. The completed Operation & Maintenance Manual shall be submitted to Kitsap County and the dispersion trench shall be inspected prior to requesting a final building inspection.
Drainage BMP: Gravelless Chamber Connect all roof drains to the gravelless chambers as shown on the approved plans. Number of chambers: Length of chambers: Where more than 1 chamber, set at a minimum of 6 foot on center 3 inches of gravel is required below the chambers. Trenches must be gravel-filled outside of the chambers to the top of the chamber louvers. The infiltration chambers shall be inspected prior to covering.
Drainage BMP: Bioretention Connect all roof drains to the bioretention cell as shown on the approved plans. Bottom Square Footage of Cell: Ponding Depth, 12” maximum: Engineered Soil Depth: 18 inches Side slopes: 3H:1V Setback, upslope from drainfield: 30 feet Setback, downslope from drainfield: 30 feet Setback from property line: 10 feet Setback from structures: 10 feet Bioretention area shall be protected to minimize compaction of underlying soils during construction. Bioretention system shall be inspected prior to requesting a final building inspection.
Drainage BMP: Rain Garden Direct runoff to rain garden, via a swale, pipe, or across landscaped area Bottom Square Footage of raingarden: Ponding depth, 12” maximum: Engineered Soil depth: 18 inches Side slopes: 2H:1V Setback, upslope from drainfield: 50 feet (raingarden handbook) Setback, downslope from drainfield: 10 feet (raingarden handbook) Setback from property line: 10 feet Setback from structures: 10 feet The rain garden shall be inspected prior to requesting a final building inspection.
Drainage mitigation method: Site Development Activity Permit (SDAP) All site plan construction and stormwater systems shall be installed as designed per SDAP #: Stormwater mitigation that does not match the approved SDAP will not be allowed without further SDAP review by Kitsap County Department of Community Development
This permit shall comply with all of the conditions of approval of the land segregation for LOT 14, PLAT OF POINT OF VIEW NO. 1, ACCORDING TO THE PLAT RECORDED IN VOLUME 11 OF PLATS, PAGES 1, 2 AND 3, RECORDS OF KITSAP COUNTY, WASHINGTON
Prior to completion of this permit with the Department of Community Development, the Applicant shall satisfy all conditions of a Right-of-Way Permit through the Department of Public Works for any and all work performed in the county Right-of-Way associated with this project. Apart from the Site Development Activity Permit (SDAP), the Right of Way permit may require extra work to comply with current Washington State Department of Transportation or Kitsap County Road Standards. You may contact Kitsap County Public Works, Right-of-Way Division at (360) 337-5777 to obtain a Right-of-Way permit.
The project shall follow the recommendations of the Geotechnical Engineering Investigation Report prepared by Resolve Environmental dated April 26, 2019 and the Geotechnical Addendum dated October 5, 2019.

Required Permits
Type Requirement For Number Status
Right of Way Permit Issue 19-03808 Finaled

Notes

Associations